NSPS Particulate Testing Requirements (40 CFR 60)
All subparts specify EPA Method 5
unless otherwise specified.
N/S = Not Specified. In these cases, either process-specific or Method
1-5 requirements would apply.
Subpart |
Facility |
Minimum Sample Time
(minutes) |
Minimum Sample Volume (dscf) |
Filter Temperature (°F) |
Comments |
D |
Fossil-fired
boilers |
60 |
30 |
320±25°F |
Method 5B
required after FGD |
Da |
Electric
Utilities |
120 |
60 |
320±25°F |
Method 5B
required after FGD |
Db |
Industrial
Boilers |
120 |
60 |
320 |
Method 5B
required after FGD
Method 17 allowed if gas temperature is less than 320°F. |
Dc |
Small
Industrial Boilers |
120 |
60 |
320 |
Method 5B
required after FGD
Method 17 allowed if gas temperature is less than 320°F. |
Ea |
Municipal
Waste Combustors, 1989-1994 construction |
N/S |
60 |
320±25°F |
|
Eb |
Municipal
Waste Combustors, constructed after 1994 |
N/S |
60 |
320±25°F |
240 minute
test specified for Dioxins |
Ec |
Hospital
Incinerators |
60 |
N/S |
N/S |
240 minute
test specified for Dioxins |
F |
Portland
Cement Mfg. |
60 |
30 |
N/S |
40.6 dscf required for Clinker Cooler |
N |
Basic
Oxygen Process, Primary Emissions |
60 |
53 |
N/S |
Integral #
of heats or blows. |
NA |
Basic
Oxygen Process, Secondary Emissions |
N/S |
200 |
N/S |
Sampling
done only during steel production. |
O |
Sewage
Treatment Facilities |
60 |
31.8 |
N/S |
|
P |
Primary
Copper Smelters |
60 |
30 |
N/S |
|
Q |
Primary
Zinc Smelters |
60 |
30 |
N/S |
|
R |
Primary
Lead Smelters |
60 |
30 |
N/S |
|
Y |
Coal
Preparation Plants |
60 |
30 |
N/S |
Sampling
must begin no less than 30 minutes after startup and end before shutdown
procedures commence. |
Z |
Ferro-Alloy
Electric Arc Furnaces (EAF) |
60 |
63.6 |
N/S |
Integral #
of furnace cycles. |
AA |
Steel EAF,
1974-1983 construction |
240 |
160 |
N/S |
Integral #
of heats if single furnace. Use Method 5D for Positive Pressure Baghouses. |
AAa |
Steel
EAF/AOD, constructed after 1983 |
240 |
160 |
N/S |
Integral #
of heats if single furnace. Use Method 5D for Positive Pressure Baghouses. |
BB |
Kraft Pulp
Mills |
60 |
31.8 |
N/S |
Use water
instead of acetone to rinse |
CC |
Glass Mfg. |
60 |
31.8 |
350±25°F |
248±25°F
if gas-fired or <0.5%w/w sulfur oil |
DD |
Grain
Elevators |
60 |
60 |
Ambient |
No heaters
allowed |
HH |
Lime Mfg. |
60 |
31.8 |
N/S |
5D for
positive pressure baghouses |
LL |
Metallic
Mineral Processing |
N/S |
60 |
<250 |
Method 17
allowed. |
NN |
Phosphate
Rock Processing |
60 |
30 |
N/S |
|
PP |
Ammonium
Sulfate Mfg. |
60 |
53 |
N/S |
|
UU |
Asphalt
and Asphalt Roofing Materials Mfg. |
120 |
106 |
N/S |
Method 5A
specifies 108±18°F |
OOO |
Non-metallic
Mineral Processing |
N/S |
60 |
<250 |
Allows
Method 17 |
PPP |
Wool
Fiberglass Insulation Mfg. |
120 |
90 |
N/S |
Method 5E
required |
UUU |
Calciners and Dryers in Mineral Processing |
120 |
60 |
N/S |
|